标签:11g The data war 考试题 planning database which stand
37、You are planning a software installation for both Oracle Database 11g Release 1 and Release 2.
You plan to have at lease one database for each release managed by Grid Infrastructure for a Standalone Server.
Which three are true in this scenario?
A) Oracle 11g Release 1 databases must be managed by Grid Infrastructure 11g Release 1.
B) Both databases can be managed by Grid Infrastructure 11g Release 2.
C) Both Oracle versions and Grid Infrastructure can be owned by the same O/S account.
D) Gird Infrastructure must be installed before both Oracle Database versions.
F) Each version of the database may be managed by a separate version of Grid Infrastructure.
F) Both Oracle versions and Grid Infrastructure can be installed under the same ORCALE_BASE.
Answer:ADE
北京CUUG整理,转载请注明,OCP讨论群:569933648/836361015
标签:11g The data war 考试题 planning database which stand